Tuesday, April 10, 2012

Standing in the Chapel


Standing in the South West corner of the Chapel looking North East.

The framing begins



The framers started in earnest on Monday April 9, 2012. The building starts to take shape.

Tuesday, March 27, 2012

Stake Center Floor Complete



The contractor has finished pouring the floor today other than the Cultural Hall. When the framing begins the building will really start to take shape.

1924 Building interior and support



The outside walls of the building are being fit with reinforcing steel which will then be sprayed with concrete. This will stabilize the building. The foundation will also be supported with concrete piers to help compinsate for the additional weight added to the building.

Saturday, March 24, 2012


The contractors began to pour the floor of the New Stake Center on March 23, 2012.

This is the West Side of the 24 building. They have patched the hole where the old stairway entered the building and have begun to frame in for the windows. They are also putting steel on the inside of the exterior walls which they will spray gunnite on to strengthen them.

Friday, March 16, 2012

AUSTRALIA ADELAIDE MISSION

Aaron Reed has been called to serve in the
 AUSTRALIA ADELAIDE MISSION 
he will report to the MTC on Aug 15, 2012. 


Congratulations Aaron you will be an awesome missionary!!