Friday, June 15, 2012


Some shots of the Stake Offices in the 1924 Building. The High Council Room and the Lobby area.







The interior of the Family History Library.
The 1924 building: The contractors had to remove the entire first layer of brick from the building. It seems the mortar was not good between the brick.


The interior framing is about done. They are not putting metal studs on the outer walls.


As you can see; the roof is on, the stone work has begun. Inside they are starting the sheet rock. The Primary room and Relief Society room are sheet rocked.

Saturday, May 19, 2012



We had Stake Conference on May 12 and 13. Elder D. Todd Christofferson from the Qurorum of the twelve and Elder Robert C. Gay of the Seventy were here. It was a great conference. We had almost a thousand people in attendance at the Sunday General Session.

This is a look at the front of the Chapel and then from the front of the Chapel to the Cultural Hall.
May 15, 2012. The roof is on and the interior framing is almost done. The electrician is working and the Mechanical is getting the A/C in. Moving right along.